IAEAが確認した福島原発における負傷者 3月16日

3月16日付けの内閣官房のプレスリリースをもとに、IAEAが確認したリストだ。日本の内閣官房のホームページに見当たらない。(探し方が悪いのかもしれない)
3月16日の内閣官房のホームページ上のトピックスは1件のみ。蓮舫大臣からの節電要請だけである。

Injuries or Contamination at Fukushima Daiichi Nuclear Power Plant

Based on a press release from the Japanese Chief Cabinet Secretary dated 16 March 2011, the IAEA can confirm the following information about human injuries or contamination at the Fukushima Daiichi nuclear power plant.


Please note that this list provides a snapshot of the latest information made available to the IAEA by Japanese authorities. Given the fluid situation at the plant, this information is subject to change.

Injuries(負傷者)

2 TEPCO(東電) employees have minor injuries
2 subcontractor(協力会社) employees are injured, one person suffered broken legs and one person whose condition is unknown was transported to the hospital
2 people are missing
2 people were ‘suddenly taken ill’
2 TEPCO employees were transported to hospital during the time of donning respiratory protection (呼吸装置の装着)in the control centre
4 people (2 TEPCO employees, 2 subcontractor employees) sustained minor injuries due to the explosion at unit 1(1号機) on 11 March and were transported to the hospital
11 people (4 TEPCO employees, 3 subcontractor employees and 4 Japanese civil defense workers(自衛隊)) were injured due to the explosion at unit 3(3号機) on 14 March

Radiological Contamination(放射能汚染)

17 people (9 TEPCO employees, 8 subcontractor employees) suffered from deposition of radioactive material to their faces, but were not taken to the hospital because of low levels of exposure
One worker suffered from significant exposure during ‘vent work,’ and was transported to an offsite center
2 policemen who were exposed to radiation were decontaminated
Firemen who were exposed to radiation are under investigation